QUÉBEC CITY, Sept. 3, 2025 /CNW/ - The Ministère des Transports et de la Mobilité durable informs road users that the Québec Bridge will be closed to traffic from September 5 at 7 p.m. to September 7 at 8 p.m. This obstruction is necessary as part of the construction of the architectural walls of the future pedestrian link linking Avenue des Hôtels to the Sainte-Foy train station.
In addition, Saint-Louis Road, between Avenue des Hôtels and Villeray Street, will be closed in both directions from September 7 to 19 to continue its reconstruction.
These interventions are part of the project to redevelop the interchanges north of the Pierre-
Laporte and Québec bridges.Traffic management
Quebec Bridge
Friday, September 5, at 7 p.m., to Sunday, September 7, at 8 p.m.
Complete closure of the Québec Bridge, in both directions.
- The sidewalk will remain open for pedestrians and cyclists.
- A shuttle bus will be available for moped riders.
- Direction Quebec City: boarding at the Presqu'île station (intersection of rue de la Mission and rue de la Presqu'île).
- Direction Lévis: boarding at the land located north of the medical clinic, on Saint-Louis Road.
- Detour: Pierre-Laporte Bridge (open at all times during the obstruction)
REMINDER - Obstructions on Saint-Louis Road
The obstructions take place in three phases, 24 hours a day, 7 days a week, according to the following schedule:
Until September 7
- Alternating traffic between Route 175 and Villeray Street.
September 7 to 19
Complete closure in both directions, between Avenue des Hôtels and Villeray Street.
- Detour:
- Eastbound: Liège Avenue, Neilson Boulevard, Hochelaga Boulevard, Lavigerie Avenue and Saint-Louis Road.
- Westbound: Lavigerie Avenue, Laurier Boulevard, Route 175 southbound and Saint-Louis Road.
From September 19 to October 24
- Traffic alternates between Route 175 and Villeray Street.
At all times during the work, access to businesses will be maintained via Chemin Saint-Louis. Pedestrians and cyclists will also be able to circulate. Signage will be installed to direct users.
Episodes of congestion are to be expected. Road users are advised to allow extra time to get to their destination. Therefore, before hitting the road, it is recommended to consult the
The Department thanks road users for their cooperation.